In 2017, the Sunshine Coast Regional District (SCRD) began a groundwater investigation to explore new groundwater supply for SCRD water users. One of the recommended options from this study was the Church Road Well Field.

The construction of the Church Road Well Field will add up to five million litres of water per day to the Chapman Water System and is a significant step forward in securing water supply for the Sunshine Coast.

Construction work on the Church Road Well Field will begin in early March 2022 and is anticipated to be completed in early Fall of 2022.

For more info, project updates, or to sign up for the project mailing list, go to Let's Talk: Church Road Well Field